L'Hay les Roses Drinking water production plant


10.12.2008

>Table of contents      Print

Drinking water production plant

Showcase for SODIMATE expertise and technology

  


The specifications of this drinking water production plant, build by OTV, required SODIMATE to bring to bear its experience in the design and installation for the storage, metering and transport of powdered reagents, slurry preparation (water and powdered activated carbon), mixers (sludge and quick lime) and sludge conveyors.


Sludge screw conveyor

Sludge & quick lime mixer

Activated carbon slurry preparation


THE CONTEXT :
Size
: 150 000 m3 / day. 
Client : Eau de Paris (S.A.G.E.P.)
One of the largest units in Europe using ultrafiltration by membrane.

The SODIMATE equipments were installed in July 2007 and commissioned in September 2008.

TECHNICAL SPECIFICATIONS :

2 sets for sludge liming :
- Discharge and metering of quicklime (Stage 1)
- Sludge mixing and transport (stage 2)
Sludge flow rate at centrifuge output 1 m3/hour with dry material content of 20 to 25%.
Liming at 30% of dry mtlerial i.e. at a rate of 20 to 100 kg of quicklime/hour

2 lots for activaled carbon:
- Discharge and metering of activated carbon
- Mixing of activated carbon with water
Slurry preparation of 2 x 4000 litres/hour of activated carbon slurry at a concentration of 20 g/l

THE SODIMATE RESPONSE :

For sludge liming :
Package 1 (picture 4): 2 sets, each including:
1 silo arch breaker/metering system, 2 conveyors and 1 injector, with 17 m length
Package 2 (pictures 1 and 2): 1 set of equipment including:
2 paddle shaft mixers, 2 sludge conveyors, 1 conveyor on motorized pivot

For activated carbon :
Package 3 (picture 4): 2 sets, certified ATEX 22, each including:
1 silo arch breaker/metering system, 2conveyors (one vertical of 4.50 m)
Package 4 (picture 3): 2 units, with ATEX 22 certification, each including :
1 wetling unit, 1 x 2000 litre slurry make-up tank with water supply ancillaries

INSTALLATION ON SITE :
Installation in 2 weeks by 4 people with 1 crane. Commissioning by two people

SODIMATEGUARANTEE:
Parts and labour guarantee for 2 years from commissioning.

DownloadPress release PDF
Size:698 kB - Last modifications: 2/02/2009
 



Table of contents

 

Homepage - Company - News - Application - Products - Catalog/Quotation Request - Download - Map of the site
© SODIMATE
Mentions Légales